3.800 m rakımda, −20 °C altında 800 yataklı iş gücü kampı
The brief
A major copper mining operation needed to scale its workforce by 800 personnel for a four-year expansion. The site sits at 3,800 m in the Chilean Andes. Winter nights drop to −20 °C, summer UV exceeds Europe's peak by 50%, and the nearest town is 180 km away over switchback roads unsuitable for oversize transport.
Müşteri kısıtlaması: dağ yolu daha geniş hiçbir şeye izin vermediğinden son aşamada her modülün standart 40 ft açık üstlü konteynerlerin içine sığması gerekiyordu. Doluluk 14 ayda tam kapasiteye ulaşmalıydı.
What we built
We designed 112 modules in three variants — 40-bed male dorm, 40-bed female dorm, 20-person staff with ensuites — every one of them sized to fit a 40-foot flat-rack in transport. Envelope: 150 mm PIR with a triple-glazed window package (U=0.9 W/m²K), rated for −25 °C continuous and the 160 km/h winter gust load. Roof: 65° pitch with snow load rating of 3.8 kN/m², because at that altitude the snow comes in sideways and stays for four months.
Every module was air-tested to 1.5 m³/h·m² at 50 Pa — a tighter envelope than most permanent buildings in the region — because at −20 °C every gap is an energy bill and a comfort complaint. MEP is fully redundant: two 250 kVA gensets per hundred beds in N+1, two water loops, two heat pumps per module zone. Modules shipped from Mersin → San Antonio by sea, then overland to the mine. Final leg was done in two convoys per week over the 12-month delivery programme.
Timeline
- Month 0Contract signature, ground survey, high-altitude envelope testing.
- Month 1–3Tasarım donduruldu, maket modül inşa edildi ve 50 Pa'da hava test edildi.
- Month 3–12Ankara'da üretim, zirve haftada 10 modül.
- Month 6–13Sea freight from Mersin → San Antonio, Chile.
- Month 7–14Ortak yapımlı kazık temeller üzerinde sahada montaj.
- Month 14Final SAT, first 400-bed phase handed over.
- Month 18Full 800-bed capacity operational.
Outcome
18. ayda tam doluluk sağlandı, müşterinin operasyonel hedefinin iki ay önünde. Ölçülen kış ısıtma tüketimi zarf hava sızdırmazlığı sayesinde tasarım tahmininin %18 altında kaldı. İlk 24 ayda yapısal veya zarf kusuru raporlanmadı.
Müşteri 2026'dan itibaren aynı standartta 320 yatak daha eklememiz için sözleşme imzaladı.